ZESCO says it might by 14 September 2024, be forced to shut Kariba North Bank Power Station, due to low water levels

2

ZESCO has announced that with water resources approaching the minimum operating level, it faces the imminent risk of depleting the remaining reserves by 14 September this year, which could result in the shutdown of the Kariba North Bank Power Station.

In a statement issued by company spokesperson Matongo Maumbi, Zesco anticipates a significant power supply gap in September, driven by a growing drought-induced hydropower generation deficit.

He said the deficit stands at 1,086 megawatts (MW) for August 2024 and is projected to increase to 1,280 MW in September 2024.

Mr Maumbi explained that the expected power supply gap in September is also attributed to annual plant maintenance by Maamba Energy.

“Maamba Energy, one of the Independent Power Producers with a total installed generation capacity of 300 MW, has scheduled annual plant maintenance to be carried out in phases,” he said.

He said in phase one, from 27 August to 10 September 2024, 150 MW of generation capacity will be unavailable while in phase two, from 16 September to 30 September 2024, an additional 150 MW will be offline.

However, Mr Maumbi noted that Zesco is facing import route constraints, including equipment failure due to faults and acts of vandalism on the Namibian route.

He said the factors are adding strain to the system, particularly during the morning peak demand period from 05:00 to 10:00 and the evening peak from 17:00 to 22:00.

Mr Maumbi said as a mitigation measure, Zesco has secured an additional 200 MW in power imports, effective 1 August 2024, to help alleviate the impact of reduced generation capacity.

“While the imports are critical, they may not be sufficient to fully balance supply and demand,” Mr Maumbi said, adding that “emergency power rationing remains a possibility, and Zesco is exploring all available options to stabilise the situation.”

(Mwebantu, Monday, August 26th, 2024).

2 COMMENTS

  1. if there was a Zambian agenda this and solutions to this would be the talk of the day and possibly sharing ideas on how to come out of this crisis because this doesn’t care what political party you belong too. instead all you hear is politics ” no HH upto 2031″ and ” Lungu is coming back”. Zambians do you realise that when we shutdown electricity water will be a problem because most of us also use the same power to pump water from boreholes?? schools and people’s jobs are in direct danger of a shut down. instead the politicians that care alot about you only focus is who is in power in 2026??? zesco is telling you we have failed and it looks like importing power won’t be possible so as at now the 2026 is talk is a none factor.? your political leaders who are supposed to provide leadership are busy on the campaign trail one in luapula the other in Zambezi telling you to get ready to vote in 2026.

  2. Political leaders in Zambia? A bunch of selfish shameless hypocritical incompetent thieving liars with only interest of personal financial betterment at the cost of National development stagnation.

LEAVE A REPLY

Please enter your comment!
Please enter your name here